Case Study: Manufacturing Throughput Crisis
Industry: Precision Manufacturing Problem Type: Operations Duration: 6 weeks Outcome: 45% throughput increase
The Situation
A precision manufacturing company producing aerospace components faced a throughput crisis. Despite significant investment in new CNC equipment, output had plateaued. Customer orders were backlogging, and the company was at risk of losing key contracts.
What we heard initially:
- "The new machines aren't performing to spec"
- "We need to add a night shift"
- "The operators need more training"
The Investigation
Week 1-2: Symptom Mapping
We started by documenting exactly what "throughput crisis" meant:
- Output: 850 units/week (target: 1,200)
- Utilization: 62% (claimed), actual TBD
- Backlog: 6 weeks and growing
- Quality: 4.2% rejection rate
Week 2-3: Process Tracing
We followed the flow from raw material to shipping:
- Material receiving: No delays observed
- Machining (3 CNC cells): High variability in cycle times
- Deburring: Manual, consistent pace
- Inspection: Significant queuing observed
- Assembly: Waiting for inspected parts
- Shipping: On-time once parts available
The inspection queue was the first clue. Parts were piling up waiting for quality verification.
Week 3-4: Root Cause Analysis
Inspection Bottleneck
The quality department had three inspectors. Inspection time averaged 12 minutes per part. Capacity: ~120 parts per day across all inspectors.
Production was capable of ~200 parts per day.
No matter how fast production ran, inspection could only process 120 parts daily. The gap accumulated as backlog.
But why was inspection so slow?
We dug deeper. Inspectors were following an outdated procedure that required:
- 23-point manual measurement
- Full documentation on paper forms
- Secondary verification for every part
This procedure was written when the company produced 15 different part numbers. They now produced 180. The procedure had never been updated.
Secondary finding: Setup time waste
While investigating, we noticed machine setup times varied wildly: 45 minutes to 4 hours for the same part. Tribal knowledge problem. Some operators knew the tricks; others didn't. See Field Note: Tribal Knowledge.
The Findings
Root cause 1: Inspection procedure misaligned with current production volume and part variety. Designed for a different era.
Root cause 2: Undocumented setup procedures leading to variable machine utilization.
Contributing factors:
- No capacity planning across departments
- Inspection treated as separate from production
- Resistance to procedure changes due to aerospace certification concerns
The Recommendations
Immediate (Week 1-2)
Risk-stratify inspection
- Not all parts need 23 measurement points
- Implement tiered inspection based on part criticality and history
- Predicted reduction: 23 points → average of 8 points
Cross-train for flexibility
- Train two production supervisors on basic inspection
- Allow overflow capacity during peaks
Short-term (Month 1-2)
Document setup procedures
- Capture best practices from experienced operators
- Create standardized setup sheets per part family
- Target: 90-minute maximum setup time
Digital inspection forms
- Eliminate paper documentation
- Reduce transcription errors
- Enable real-time quality tracking
Medium-term (Month 2-4)
Capacity alignment
- Match production scheduling to inspection capacity
- Eliminate production of parts that will sit in queue
Quality engineering review
- With aerospace auditor present
- Formally revise inspection procedures
- Certify the streamlined process
The Implementation
The client implemented recommendations 1-4. Recommendation 5 was partially implemented. Recommendation 6 was deferred due to an upcoming customer audit.
The Outcome
After 3 months:
- Output: 1,240 units/week (target exceeded)
- Utilization: 78%
- Backlog: 2 weeks (within normal)
- Quality: 3.8% rejection rate (improved)
Quantified impact:
- 45% throughput increase
- $2.1M additional annual revenue capacity
- 0 new equipment purchases needed
- 0 additional headcount required
Key Lessons
The bottleneck was invisible
Everyone was looking at production. The constraint was in quality. See Field Note: Finding the Bottleneck.
Procedures fossilize
What was appropriate 10 years ago wasn't appropriate today. But no one had questioned it. "That's how we've always done it."
Documentation matters
The setup time variability was pure tribal knowledge. Once captured, the benefit was immediate.
Systems, not people
The inspectors weren't slow. The procedure was wrong. The operators weren't inconsistent. The knowledge transfer was missing.
The solution to a production problem was found in the quality lab.